One cubic yard holds 27 cubic feet, so multiply length × width × depth in feet and divide by 27 — or divide feet × feet × inches by 324. A 12 × 20 ft slab 4 in thick is 2.96 cubic yards, about 6 tons of concrete once it is poured.
What a cubic yard is and the formula that covers most jobs
A cubic yard is a cube 3 ft on every edge: 3 × 3 × 3 = 27 cubic feet, which is 46,656 cubic inches. That single unit is how bulk material is bought in the US — ready-mix concrete, crushed stone, topsoil, sand, mulch and fill dirt are all quoted, delivered and billed by the cubic yard. NRMCA's ordering guide for ready-mix states it plainly: concrete is sold by volume, in cubic yards of freshly mixed, unhardened concrete.
Every estimate starts with the same three measurements — length, width and depth — and the same division:
Cubic yards = length (ft) × width (ft) × depth (ft) ÷ 27
Depth is the measurement that trips people up, because plans, bags and job specs quote it in inches while the footprint is taped in feet. Divide the depth by 12 before multiplying, or fold both conversions into one divisor: 12 × 27 = 324, so cubic yards = length (ft) × width (ft) × depth (in) ÷ 324.
A 12 ft × 20 ft pad at 4 in thick, worked both ways: (12 × 20 × 4) ÷ 324 = 2.96 cubic yards. Checking it the long way, 240 sq ft × 0.333 ft = 80 cubic feet, and 80 ÷ 27 = 2.96. Add the usual 10% waste allowance and the order becomes 3.26 cubic yards.
Not every job is a rectangle. The same volume logic handles the rest:
- L-shaped driveway or patio: split the outline into two rectangles, run each one, add the results.
- Round footing, pier or post hole: π × radius² (in feet) × depth (ft) ÷ 27. A 12 in diameter hole 3 ft deep is 3.14 × 0.25 × 3 = 2.36 cubic feet, or 0.09 cubic yard — about four 80 lb bags of mix.
- Triangular bed or gable area: 0.5 × base × height for the area, then multiply by depth and divide by 27.
- Multiple beds or footings: convert each one to cubic yards first, then add — never add inches to feet.
Two errors explain most short pours. The first is reading "a yard" as 3 linear feet or 9 square feet; it is always a cubic yard of volume, which is why 2.96 cubic yards fills a 240 sq ft patio at 4 in but only 80 sq ft of a wall poured 12 in thick. The second is thickness drift: an extra 1/8 in of depth on a 4 in slab uses roughly 3% more concrete, and on a 10-yard order that is a third of a yard you did not plan to pay for.
Cubic feet, cubic inches and cubic yards: the conversion table
All three volume units are locked together by fixed definitions, not by rules of thumb: a foot is 12 inches on each edge, so one cubic foot is 12 × 12 × 12 = 1,728 cubic inches, and a yard is 3 feet on each edge, so one cubic yard is 27 cubic feet. Nothing about those factors changes with material, region or year.
| Volume | Cubic feet | Cubic inches | Cubic yards |
|---|---|---|---|
| 1 cubic foot | 1 | 1,728 | 0.037 |
| 10 cubic feet | 10 | 17,280 | 0.37 |
| 1 cubic yard | 27 | 46,656 | 1 |
| 2 cubic yards | 54 | 93,312 | 2 |
| 5 cubic yards | 135 | 233,280 | 5 |
| 10 cubic yards | 270 | 466,560 | 10 |
Which unit you need depends on how the material is sold, and this is where estimates go wrong. Bulk delivery is always priced by the cubic yard, so that is the number the supplier wants. Bagged products are labeled in cubic feet, so the cubic-foot line is the one to divide by the bag size: a 2 cubic foot bag of mulch means 27 ÷ 2 = 13.5 bags per yard, and a 0.75 cubic foot bag of soil means 36. Small castings and box dimensions are given in inches, so the cubic-inch line is the useful one there.
Converting the other way is just as common on a job site. A supplier quotes 6 yards and you want to know whether it fits the trailer: 6 × 27 = 162 cubic feet. A bag says 1.5 cubic feet and you want yards: 1.5 ÷ 27 = 0.056 cubic yard, which is why bags only make sense on small work.
Coverage: how many square feet one cubic yard covers
Once the depth is fixed, a cubic yard becomes a coverage figure: divide 27 cubic feet by the depth in feet and you get the area one yard will cover. That is the fastest way to sanity-check a mulch, topsoil or gravel order before you call.
| Depth | Coverage per cubic yard | Typical use |
|---|---|---|
| 1 in | 324 sq ft | Topdressing a lawn, dust control |
| 2 in | 162 sq ft | Refreshing an established mulch bed |
| 3 in | 108 sq ft | Standard mulch depth, garden paths |
| 4 in | 81 sq ft | New beds over bare soil, gravel paths |
| 6 in | 54 sq ft | Topsoil for a raised bed, gravel base |
| 12 in | 27 sq ft | Fill dirt, planting beds built up a foot |
The relationship is strictly inverse, which is the part people underestimate: doubling the depth halves the coverage. A yard of mulch spread 3 in deep covers 108 sq ft; spread 6 in deep, the same yard covers 54 sq ft. That is why a bed you have been topping up at 2 in for years suddenly needs twice the material when you decide to smother weeds with a 4 in layer.
Run a real bed: 40 ft × 6 ft at 3 in deep is 240 sq ft, and 240 ÷ 108 = 2.22 cubic yards, or about 30 bags of 2 cubic foot mulch. The same arithmetic on a vegetable bed built up 6 in: 30 ft × 10 ft = 300 sq ft ÷ 54 = 5.56 cubic yards of topsoil, which at roughly 80 lb per cubic foot is about 12,000 lb, or 6 short tons, to move by hand or by wheelbarrow.
What a cubic yard weighs: concrete, gravel, soil and mulch
Suppliers sell by volume and haulers bill by weight, so every cubic-yard order has two numbers attached to it. Convert between them with the material's density: pounds per cubic yard = pounds per cubic foot × 27, and short tons = pounds ÷ 2,000.
| Material | Density (lb/ft³) | Weight per cubic yard | Short tons per yard |
|---|---|---|---|
| Normal-weight concrete | 140–150 | 3,780–4,050 lb | 1.89–2.03 |
| Gravel, dry | 105 | 2,835 lb | 1.42 |
| Gravel, wet | 125 | 3,375 lb | 1.69 |
| Sand, dry | 97 | 2,619 lb | 1.31 |
| Dirt, loose dry | 76 | 2,052 lb | 1.03 |
| Loam / topsoil | 80 | 2,160 lb | 1.08 |
Concrete is the heaviest common material on the list. Engineering ToolBox puts normal-strength concrete at 140 to 150 lb per cubic foot, so a yard lands between 3,780 and 4,050 lb — call it two short tons. That is the weight the formwork, the subgrade and the delivery truck all have to carry, and NRMCA notes that a loaded concrete truck weighs about 80,000 lb, which is why access and a firm, unobstructed path matter on delivery day.
Gravel sits at roughly 1.4 tons per yard when dry, which is the figure HomeGuide uses when it converts yards to tons for a driveway quote — and 1.7 tons when the stone is wet. Soil is lighter again: loose dry dirt at 76 lb per cubic foot is about 1 ton per yard, while topsoil at 80 lb per cubic foot is 2,160 lb. Moisture, not the material name, moves these numbers most, so a load dug after a week of rain can weigh 20% more than the same volume dug dry.
Weight is what decides the logistics. A 24 ft × 24 ft driveway at 6 in thick is 576 sq ft × 0.5 ft = 288 cubic feet = 10.67 cubic yards; in stone that is 10.67 × 1.42 = about 15.1 tons, more than the 8 to 10 cubic yards a single 10-wheel dump truck hauls in one trip. The same volume in concrete is 21.6 tons, and it arrives in one mixer rated for 8 to 12 cubic yards.
Bags, bulk or truckload: how to order cubic yards without coming up short
Volume from the plan is the theoretical minimum, never the order. NRMCA's guidance for ready-mix is that the quantity ordered should be 4% to 10% more than an estimate calculated from plan dimensions to cover contingencies. Use 10% for a DIY pour, uneven subgrade or over-excavated footings, and 5% for clean, well-braced forms. On the 2.96 cubic yard patio that is 3.11 to 3.26 cubic yards; on a small 40 ft × 6 ft mulch bed at 3 in, 10% adds about 0.22 cubic yard, which is six extra bags.
Then pick the packaging. Bagged concrete yields by volume, not by weight: QUIKRETE's data sheet for its 80 lb Crack Resistant mix states a yield of approximately 0.6 cubic feet of mixed concrete per bag, so 27 ÷ 0.6 = 45 bags per cubic yard. That is close to 3,600 lb of material opened, mixed and placed by hand, which is the point where a truck starts winning on labor alone. Mulch flips the crossover the other way — 13.5 bags of 2 cubic feet equal a yard, and bagged mulch stays competitive for single beds.
| Job | Cubic yards | +10% waste | Weight | Buy as |
|---|---|---|---|---|
| Patio, 12 × 20 ft, 4 in concrete | 2.96 | 3.26 | 13,200 lb | One short load or 147 bags of 80 lb |
| Driveway, 24 × 24 ft, 6 in gravel | 10.67 | 11.74 | 16.7 tons | Two dump truck loads |
| Mulch bed, 40 × 6 ft, 3 in | 2.22 | 2.44 | Rarely weighed — sold by volume | One scoop delivery or 33 bags |
Truck capacity sets the order size. NRMCA puts truck mixer capacity at 8 to 12 cubic yards, so a 10.67 cubic yard driveway pour fits one truck with a little margin for the waste allowance. For loose material, HomeGuide reports that a 10-wheel dump truck carries 12 to 20 tons of gravel, or roughly 8 to 10 yards depending on the stone — which is why a 11.74 cubic yard driveway order splits into two deliveries rather than one. Finally, recheck the volume as the pour or the spread progresses and tell the supplier early if you are running short; a small clean-up load at the end costs far more per yard than the material itself.
What a cubic yard costs in 2026
Pricing is quoted per cubic yard, and the spread between materials is wider than most people expect. Ready-mix concrete ran a nationwide average of $179.95 per cubic yard in 2025 and sits at $160 to $195 or more per cubic yard in 2026, before delivery add-ons. Crushed stone and gravel are an order of magnitude cheaper per yard: $15 to $75 per cubic yard, with a national average around $60, delivered in standard service areas.
| Order | Cubic yards | Unit price | Material cost |
|---|---|---|---|
| Ready-mix, 12 × 20 ft patio at 4 in, with 10% waste | 3.26 | $180/yd | About $587 |
| Gravel, 24 × 24 ft driveway at 4 in | 7.11 | $60/yd | About $427 |
| Gravel, 12 × 100 ft road at 12 in of layers | 44.44 | $60/yd | About $2,666 |
| Ready-mix, 24 × 24 ft garage slab at 4 in, with 10% waste | 7.82 | $180/yd | About $1,408 |
Two structural costs sit on top of the per-yard price. Delivery minimums bite on small orders: HomeGuide puts a full truck load of gravel at $1,350 or more with a 10 cubic yard minimum, so a 2 cubic yard path pays a rate per yard nobody advertises. On the concrete side, ordering under a full mixer load brings short-load charges, and the per-square-foot alternative hides the material entirely — a plain slab poured by a contractor runs $6.50 to $10.50 per square foot installed, which for the 240 sq ft patio is $1,560 to $2,520, against roughly $587 of concrete. The gap is forming, subbase, finishing and labor, not the yards.
Under about one cubic yard, bags usually beat delivery even at a higher price per cubic foot, because a delivery minimum costs more than the material. Past two or three yards, bulk wins on price and on the time you would otherwise spend mixing.
Frequently asked questions
How do I calculate cubic yards from feet and inches?
Multiply length × width × depth in feet and divide by 27. If the depth is in inches, either divide it by 12 first or use the shortcut of dividing feet × feet × inches by 324. A 12 × 20 ft slab at 4 in is (12 × 20 × 4) ÷ 324 = 2.96 cubic yards.
How many cubic feet are in a cubic yard?
27. A yard is 3 ft on each edge, so 3 × 3 × 3 = 27 cubic feet, which is 46,656 cubic inches. Divide any cubic-foot figure by 27 to get yards, and multiply yards by 27 to go back.
How many square feet does a cubic yard cover?
It depends on depth: 324 sq ft at 1 in, 162 sq ft at 2 in, 108 sq ft at 3 in, 81 sq ft at 4 in, 54 sq ft at 6 in, and 27 sq ft at 12 in. Divide 27 cubic feet by the depth in feet to get the coverage for any other depth.
How much does a cubic yard of dirt or topsoil weigh?
Loose dry dirt is about 76 lb per cubic foot, so a cubic yard is roughly 2,050 lb, or about 1 short ton. Topsoil or loam at 80 lb per cubic foot is 2,160 lb per yard. Wet material can weigh 20% more, so confirm tonnage with the supplier if the load is being weighed.
How many 80 lb bags of concrete make a cubic yard?
About 45. An 80 lb bag yields roughly 0.6 cubic feet of mixed concrete, and 27 ÷ 0.6 = 45. With a 10% waste allowance, plan on 50 bags per yard.
How many cubic yards does a dump truck or concrete mixer hold?
A concrete truck mixer holds 8 to 12 cubic yards. A 10-wheel dump truck carries roughly 8 to 10 cubic yards of gravel, or 12 to 20 tons depending on the stone. Weight limits, not volume, are usually the real constraint on dense material.
Sources
- NRMCA — CIP 31, Ordering Ready Mixed Concrete (PDF)
- QUIKRETE — Crack Resistant Concrete Mix data sheet, Product No. 1006-80 (PDF)
- The Engineering ToolBox — Concrete Properties: density 140–150 lb/ft³
- The Engineering ToolBox — Densities of dirt, mud, gravel and sand
- HomeGuide — Crushed stone and gravel prices per ton, yard and truck load
- Concrete Network — Concrete Prices 2026: how much is a yard of concrete